Laying the Sand Layer Return to index

After you have preped the base, it is time to lay the sand layer.

NOTE: It is important to keep your sand dry. Always your sand covered in case of rain.

Do not attempt to level any area or surface irregularities with the sand. This will result in an uneven surface and unwanted settling.

Lay your screed guides (l" (25mm) electrical conduit,1" strips of wood or other suitable rigid 1" guide) 4' to 6' apart and parallel. Work from side to side with your screed guides, screed a 10' section of sand. You will use your 6 ft. to 8 ft. 2" x 6" to loosely spread the sand and to strike off any excess. DO NOT walk on or work from your screeded sand. Do not worry about voids that screed guides have left after you have removed them. You will lightly fill them with sand and trowel them smooth as you are laying the pavers.